|
|
|
Notice Information Q.
What Dam Project is being considered at the Special Meeting? A.
The Dam Project is to replace
a crushed pipe and valve beneath a portion of the dam used to lower the lake for
maintenance and emergencies. It includes removing the existing low level outlet
works, installing a new 42" concrete outlet pipe, installing a new sluice
gate, constructing a concrete intake structure with a trash rack, and
constructing a riprap scour hole at the pipe outlet. Also, the brush and other
tree growth on the back (non lake) side of the earthen dam will be cut and
removed. Q.
Why is this Project necessary? A.
During the very heavy rains that occurred in October 2005 high downstream
water conditions broke off a section of the old 21" metal low level outlet
pipe. An inspection of the pipe revealed that it was in very poor condition, was
rusted and leaking. Also, it is not possible to completely shut off the valve to
stop water flow through the existing drainage pipe. Water is continuing to erode
the dam around the area of the existing drainage pipe. Also, the earthen dam is currently in violation of
Department of Environmental Protection (DEP) regulations on the issue of water
control, and the growth of vegetation on earthen dam. While the DEP has not
taken any official action to date on these issues, the DEP is aware of the
conditions and is aware the Tax District is currently planning to correct both of these
problems. Q.
Has this Project been approved? A.
Yes, the Board of Directors hired J & D Civil Engineers to develop
the plans for the project and the plans were submitted to. DEP has approved the
project and issued the required permits. Q.
Will the new drainage system be the same as the existing drainage? A.
No, the project proposes to replace the existing 21" low level
outlet pipe and gate structure with a new 42" pipe and sluice gate structure
at the same location. Q.
Why is the Project increasing the drainage pipe size? A.
The reason that the Tax District would like to increase the size of the
pipe is because Q.
Will the lake be drained during the construction? A.
The intention is to block off the construction
area with a temporary coffer dam to perform the work in dry conditions. Therefore, the
water level in the lake will not be lowered during construction. Q.
What would happen if nothing is done? A.
In the short term probably nothing would happen but over time the water
will continue to erode the earthen dam around the defective outlet pipe to the
point that the earthen dam could breach and the lake waters would drain out of
the lake, leaving a muddy area in place of the lake.
Also, it is not possible to lower the lake or to control the water level
at this time due to the current valve is not operable. Q.
When would it happen? A.
That time period is not known, however, with heavy rains and higher lake
water levels the erosion rate increases and the already eroded pipe will
eventually cause the dam to be breached. Q.
What is the cost of the Project? A.
The project cost estimates
from a number of contractors range from $200,000 to $350,000. All the estimates
state that there may be additional costs (cost over runs) if unknown problems
occur during the construction project. Q.
How does the Board of Directors propose to pay for the project? A.
Since the cost is much more
than the District has in reserve funds, the Board of Directors are proposing
that a loan from a bank be secured for the funding of the project. The loan
would be for 5 to 15 years depending on input from the voters at this special
meeting of the Tax District. Q.
How will the loan be paid back? A.
The Board of Directors is
recommending that the loan payments would be including in the annual budget of
the Tax District. The mill rate would be increased to cover the loan payments
for the period of the loan. The amount of the increase will depend upon the
actual loan amount and the interest rate of the loan. At this time it is
estimated that the mill rate increase would be approximately 1 to 1.25 mils or
$100 per year for $100,000 of assessed value of your property. Q.
Will there be a special tax this year? A.
No, there is presently
sufficient monies in the Capital Improvement Fund to pay the loan payments for
the remainder of the fiscal year which ends on June 30, 2009. Q.
Is there any State or Federal Funds available for the Project? A.
The State of Connecticut
Department of Environmental Protection has funds for municipal flood and erosion
control projects. For this year approximately $7 million in funding was
available however more than $4.5 million has been given to other towns and
cities in Q.
If Witches Woods Tax District receives these funds, what would happen to
the money? A.
The funds would be used to
pay down the bank loan. Q.
Does the board have a recommendation on the proposed issue? A.
The Board of Directors urges all Tax District members to attend this
meeting, and to become familiar with the issues. We recommend a vote to approve
these necessary repairs and funding in order to preserve the quality of our
beautiful lake. |